US ITER: DRGA Analysis Station Design Build

Category: Fabrication and Machining Services
Small Business Set-Aside: TBD
Estimated Value: TBD
NAICS Code: 332999
Expected Issue Date: September 28, 2026
Expected Award Date: November 9, 2026
Contact Name: Travis Olinger
Contact Email: olingertj@ornl.gov

Please reach out to the Procurement Officer whose email address is shown above. Inform them of your interest in being placed on the bid list for this requirement. You may also send your capability statement, preferably one page.

Design, validation, fabrication, inspection, packaging and preparation for the shipment of both EP11 and LP12 DRGA Analysis Stations. The seller is expected to demonstrate that the proposed design will meet the technical requirements through design review. This procurement may be executed in tow phase" (1) Design Phase and (2) Fabrication Phase.
 

Design of EP11 Analysis Station includes:
-Analysis Station Frame
-Analysis Chamber (including pipes, gate valves, flanges, pressure gauges, QMS, magnetic shielding, etc.)
-Inter-Pump Volume & Forline (including pipes, flanges, orifice, pumps, pressure gauges, plasma cells, magnetic shielding, etc.)
-Calibration Gas System (including pipes, bottles, isolation valves, etc.)
-Enclosure
 

Design of LP12 Analysis Station includes:
-Analysis Station Frame 
-Analysis Chamber (including pipes, gate valves, flanges, pressure gauges, QMS, magnetic shielding, etc.)
-Inter-Pump Volume & Foreline (including pipes, flanges, orifice, pumps, pressure gauges, plasma cells, magnetic shielding, etc.)

The technical specifications [3.1.2][3.1.3] and [3.1.4] provide a detailed classification by component. All deliverables must follow the DRGA Quality Plan [3.1.5] and applicable requirements in the ITER Vacuum Handbook [3.1.6]. Cable Block Diagrams (CBD) will be provided for EP11 [3.1.7] and LP12 [3.1.8]. Piping and Instrumentation Diagram (P&ID) will also be provided for EP11 [3.1.9] and LP12 [3.1.10]. General Arrangement (GA) Drawings will be provided [3.1.11] and [3.1.12].

Statement of Work